Project

Victory Plaza

Redesigning in-situ concrete frame for innovative, fast-track build MMC approach

Walsh identified several key savings across the development the most significant was to change the piling and reduce the tower core sizes. These savings along with a proactive approach won the contract with Mace for the implementation of the development.

Walsh commenced work on the N08 project following a design review of the stage D plans at the request of project managers Arcadis. The developer had engaged with Mace and Walsh won the implementation of the project through a value engineering review of the proposed structural plans.

During the design development of stage E works, Mace introduced a new building concept ā€œthe rising factoryā€. This form of construction was a radical departure from traditional concrete frame high-rise building. The rising factory or jump factory is to build a steel warehouse over the tower footprint which is supported on jacks located on the corner columns of the tower. This created an indoor construction site ā€“ improving noise, reducing safety risks and preventing environmental delays.

Within the warehouse, two travelling cranes hoist all building materials up into itself. This enables the structure to be built with the cladding, the bathroom pods, the risers, utility cabinets and partitions, all within an enclosed environment.

To enable the rising factory Walsh worked with Mace to convert the building from an in-situ concrete frame to a fully precast frame, using omina flat slabs and cores built in twin wall.

Redesigning the project for an MMC approach allowed each floor to be installed (bar second-fix, decorating and FF&E) in just one week delivering programme savings. 98% of each floorplate was constructed off-site which dramatically reduced defects. Learnings along the way meant that the final floors took just 39 hours to complete.

Client 
  • GetLiving
  • Qatari Diar Delancy
Architect 
  • LDS
Contractor 
  • Mace
Completion Date2018

Please click on images below to open a full-screen gallery.

Explore Related Projects

Student Accommodation

Chapter London Bridge

Innovating city student living through MMC [...]

Read more

Student Accommodation

Wembley Park Plot NE01

Using lean design to reduce embodied carbon on large PBSA scheme [...]

Read more

Residential

Paddington Green Police Station

Wind-tunnel testing and temporary works design reduces high-rise concrete volumes & embodied carbon [...]

Read more

Hotels

Quay House

Integrated engineering approach delivers elegant & sustainable hotel design [...]

Read more

Mixed Use

Harold Hill Family Welcome Centre

Structural scheme designed for future-proof adaptation [...]

Read more

Student Accommodation

Palmerston Court

MMC innovations & Passivhaus standards [...]

Read more

Taking Sustainability Seriously

Sustainability is in our DNA and we have our own ambitious goals to achieve Net Zero as a business and with our designs. With innovative in-house monitoring tools, Walsh clients have seen on average reductions of 10-20% total embodied carbon, with some of our flagship work achieving 60-70% reductions compared with baseline figures.